This plan represents the development of the LINCDIRE website and eportfolio platform. This project started on June 1st, 2016 and is ongoing.

Documents

No documents at this time.

Project Progress

75%

1. Initial Software Platform Construction Complete 100% Tasks 4 / 4 Comments

100%

4 of 4 completedTasks

  • Live Site, Dev Site and Site Template Domain Setup · July 10, 2016
  • WP Install · July 10, 2016
  • Manage WP Dashboard Setup · July 10, 2016
  • Setup Secure Hosting · July 10, 2016

2. CF Model Integration, Site Planning & Wireframing Complete 100% Tasks 8 / 8 Comments

100%

8 of 8 completedTasks

  • Initial Project Workflow Semantic Charts · July 10, 2016
  • Initial Teacher Site, Class Site, ePortfolio Wireframe · July 10, 2016
  • Initial CF Model Integration Planning · July 10, 2016
  • FInal CF Model Integration Plans · July 22, 2016
  • Final LMS & Task Design · July 22, 2016
  • Final Teacher Site Wireframe · July 22, 2016
  • FInal Class Site Wireframe · July 22, 2016
  • Final ePortfolio Wireframe · July 22, 2016

3. Platform Backend Development Complete 100% Tasks 5 / 5 Comments

100%

5 of 5 completedTasks

  • Project Management Plugin Tool Setup · July 15, 2016
  • Initial Main Site Updates · July 15, 2016
  • Teacher Dev Site Backend · July 29, 2016
  • Class Site Template Backend · July 29, 2016
  • ePortfolio Template Backend · July 29, 2016

4. Initial Frontend Development Complete 100% Tasks 3 / 3 Comments

100%

3 of 3 completedTasks

  • Media Compilation · August 5, 2016
  • Initial Styling · August 12, 2016
  • CF Model Portal · August 12, 2016

5. Input content Complete 67% Tasks 2 / 3 Comments

67%

2 of 3 completedTasks

  • Input Tasks into LMS & Task Bank · August 19, 2016
  • Input Evaluations into LMS & ePortfolio Template · August 19, 2016
  • Input Teacher Resources & Training Guides into Teacher Site · August 19, 2016

6. Final Frontend Development Complete 50% Tasks 1 / 2 Comments

50%

1 of 2 completedTasks

  • Final Platform-wide Styling · July 29, 2016
  • Begin Styling Age-specific Pilot Sites & ePortfolios · July 29, 2016

7. Launch / Implementation Complete 0% Tasks 0 / 3 Comments

0%

0 of 3 completedTasks

  • Assign Class Sites · July 31, 2016
  • Clone & Assign ePortfolios · July 31, 2016